Syria, Iraq move to revive strategic Kirkuk–Baniyas oil pipeline
Syria and Iraq are moving to revive the strategic Kirkuk–Baniyas oil pipeline after more than two decades of inactivity.
-
An Iraqi worker operates valves in Nihran Bin Omar field north of Basra, 550 kilometers southeast of Baghdad, Iraq, on January 12, 2017. (AP)
Syria and Iraq are advancing plans to restart the long-idled Kirkuk–Baniyas oil pipeline, a strategic artery linking Iraq’s northern oil fields to Syria’s Mediterranean coast. Inactive since 2003, the project is framed by both governments as a cornerstone of renewed bilateral energy cooperation, with reported backing by the United States potentially easing the path for international investment.
Extensive damage, full-scale rehabilitation required
Syria’s Deputy Energy Minister for Oil Affairs, Ghiath Diab, said that most pumping stations along the route have been destroyed and will require comprehensive rehabilitation.
This includes replacing pipelines, storage tanks, pumps, electrical systems, and associated civil works. Diab said refurbishing the existing line in parallel with constructing a new one would improve economic feasibility and long-term operational efficiency.
He added that Damascus is updating oil and investment legislation, encouraging public–private partnerships, and moving to activate the Syrian Oil Company to manage national petroleum resources, alongside efforts to expand renewable energy projects.
Read more: Syria plans to double natural gas output by end of 2026
Baghdad, Damascus accelerate technical coordination
Ahmed Qabbahji, deputy CEO of the Syrian Petroleum Company, said Damascus and Baghdad are moving quickly to rehabilitate the line, which would give Iraq direct access to European markets via the Mediterranean. He noted that joint Syrian–Iraqi technical committees are conducting detailed engineering assessments to determine whether to repair the existing route or develop an alternative aligned with current security and infrastructure realities.
According to Qabbahji, Syrian Petroleum has already received investment proposals from both domestic and international companies, reflecting growing interest in the project’s strategic and commercial potential.
Strategic route with regional implications
Stretching roughly 800 kilometres, the Kirkuk–Baniyas pipeline has a current design capacity of 300,000 barrels per day. Preliminary plans, however, envision a dual-line system capable of transporting up to 1.5 million barrels per day, equipped with modern pumping and monitoring stations. Proposed upgrades also include rerouting parts of the old line in Deir Ezzor to a shorter path south of Homs.
Field committees of engineers from both countries are re-evaluating the route amid assessments that show severe damage from years of neglect, war-related destruction, corrosion, and theft. Initial estimates place reconstruction costs above $4.5 billion, with construction expected to take around 36 months.
Long history, renewed urgency
One of the oldest export routes in the region, the Kirkuk–Baniyas pipeline began operations in 1952 and functioned continuously until 1980, before disruptions during the Iran–Iraq War. It resumed in 1997, halted again in 2003, following the American invasion of Iraq, and saw a failed rehabilitation attempt under a 2007 Iraq–Syria agreement that was cancelled two years later due to high costs. Limited pumping in 2010 ended amid the conflict in Syria, while a 2019 revival initiative stalled as regional dynamics redirected Iraqi flows elsewhere.
Despite repeated setbacks, both governments now view the pipeline as vital: for Iraq, a sovereign outlet to Mediterranean export markets; for Syria, a key source of revenue, infrastructure revival, and economic recovery at a crucial time.
Read more: Syria to dismantle Homs oil refinery, build modern new plant