Al Mayadeen English

  • Ar
  • Es
  • x
Al Mayadeen English

Slogan

  • News
    • Politics
    • Economy
    • Sports
    • Arts&Culture
    • Health
    • Miscellaneous
    • Technology
    • Environment
  • Articles
    • Opinion
    • Analysis
    • Blog
    • Features
  • Videos
    • NewsFeed
    • Video Features
    • Explainers
    • TV
    • Digital Series
  • Infographs
  • In Pictures
  • • LIVE
News
  • Politics
  • Economy
  • Sports
  • Arts&Culture
  • Health
  • Miscellaneous
  • Technology
  • Environment
Articles
  • Opinion
  • Analysis
  • Blog
  • Features
Videos
  • NewsFeed
  • Video Features
  • Explainers
  • TV
  • Digital Series
Infographs
In Pictures
  • Africa
  • Asia
  • Asia-Pacific
  • Europe
  • Latin America
  • MENA
  • Palestine
  • US & Canada
BREAKING
Al Mayadeen's correspondent: 15 civilians killed or wounded, including women and children, in Saudi airstrikes on Taiz districts of Khadir, Sabir al-Mawadim, Jabal Habashi, and Haifan
The Yemeni source: Saudi airspace is dangerous and unsafe, except for the airspace of Mecca and Medina.
Yemeni military source tells Saba news agency that Sanaa renews its warnings to airline companies and investors to keep their distance from airports and oil facilities.
Trump to Fox News: The US will sink Iranian ships if they attempt to break the blockade
US President Trump tells Fox News he's inclined to resume strikes against Iran after the new year if no deal is reached
More than 12 drone boats intercepted off the coast of Benghazi by Libyan naval and air forces: Two Libyan military sources
Commercial vessel flying Maltese flag targeted by suicide drone boat off the coast of Libya's Benghazi: Two Libyan military sources
IRGC: The US drone shot down by Iranian air defenses was an advanced MQ-1 ER (Extended Range) reconnaissance and combat drone
Iran's IRGC: We shot down a US MQ-1 drone east of the Strait of Hormuz, the 20th of its kind to be downed
Yemeni Armed Forces: We targeted a radar installation in the Al-Dawasir area, south of Riyadh, in two successive waves, successfully achieving the operation’s objective

UK AI data centers turn to gas amid grid connection delays

  • By Al Mayadeen English
  • Source: The Guardian
  • 18 May 2026 14:38
5 Min Read

Britain’s AI expansion is driving a growing shift toward gas-powered data centers as developers struggle with long delays connecting to the national electricity grid.

Listen
  • x
  • Fans that are part of a cooling system are seen on the roof of a data center, Monday, April 27, 2026, in Hillsboro, Ore. (AP Photo/Jenny Kane)
    [For illustration purposes] Fans that are part of a cooling system are seen on the roof of a data center, Monday, April 27, 2026, in Hillsboro, Ore. (AP)

Britain’s growing push to expand artificial intelligence infrastructure is driving a wave of plans for gas-powered data centers, The Guardian reported, as officials, energy experts, and climate advocates warn the trend could undermine the country’s clean energy goals and deepen broader concerns over mounting global energy pressures linked to the rapid expansion of AI.

The debate comes amid growing warnings worldwide that aging grid infrastructure, rising electricity demand, geopolitical instability, and the explosive growth of AI are creating new strains on energy systems. Governments and major technology firms are pouring hundreds of billions of dollars into AI development, while countries simultaneously attempt to electrify transport, expand semiconductor manufacturing, and reduce carbon emissions.

Grid bottlenecks fuel gas shift

Industry representatives and regulators speaking at the All-Energy conference in Glasgow warned that mounting strain on the UK electricity grid is pushing developers toward fossil fuel generation as an alternative power source for large AI facilities.

"There’s 100GW of datacentre projects in the queue," said Stuart Okin, director of cyber regulation and AI at Ofgem.

"Clearly that’s not all going to be able to connect [to the grid]. If a project isn’t going to get a connection, it is going to have to come up with an alternative method."

The remarks reflect growing concern within Britain’s energy sector over whether existing infrastructure can support the rapid expansion of energy-hungry AI operations.

Silvia Simon, head of research at Future Energy Networks, said gas suppliers have seen a sharp rise in requests from data center operators seeking direct access to gas networks.

"Gas networks are seeing a lot of interest from datacentre developers looking to secure a gas connection," she said. "Not just for resilience, but for primary supply. So this is already an indication that they’re really struggling to get through to the electricity networks."

According to Simon, more than 100 gas connection requests tied to data center developments have been submitted over the past two years, representing annual energy demand exceeding 15 terawatt hours.

Analysts have increasingly warned that AI infrastructure may become one of the largest new sources of electricity demand globally, with countries facing growing competition over power generation capacity, natural gas supplies, transmission infrastructure, and cooling resources needed to support hyperscale data centers.

Permanent fossil fuel generation

Energy consultants and industry figures attending the conference said developers are increasingly considering permanent gas-powered generation rather than temporary backup systems traditionally used during outages or grid delays.

"Using gas networks was previously avoided due to carbon, permitting, and land-take impacts, and has typically only been considered as a temporary fix," one consultant familiar with the sector said.

But developers are now increasingly turning to fossil fuels, "in some cases requesting over 100MW of gas power on a permanent basis."

Similar trends have emerged in the United States, where major AI-linked data center projects associated with companies including Microsoft, Meta, OpenAI, and xAI have fueled soaring electricity demand and growing reliance on gas-fired generation.

Climate targets under pressure

The expansion of gas-powered AI infrastructure is also beginning to raise questions about Britain’s long-term climate commitments.

Julian Leslie, director of strategic planning at the National Energy System Operator, said the growing reliance on fossil fuels by data centers could complicate the government’s Clean Power 2030 ambitions.

"The target was to get less than 5% of unabated gas supplying electricity in the system," Leslie said.

"But obviously if we’ve got datacentres not connected to electricity but powered by unabated gas then it does raise an interesting question about what that means for the Clean Power 2030 target."

British authorities say reforms are underway to speed up electricity connections for viable projects, while discussions continue over whether strategic sectors such as AI should receive priority access to grid infrastructure.

"The growth of artificial intelligence is affecting many aspects of life including energy – this includes an associated growth in data centres," said Eleanor Warburton, Ofgem’s director for energy system design and development.

"Connections are being delivered, but the system must work better for projects that are viable and ready to proceed."

Climate backlash grows

Climate groups, meanwhile, warned that expanding AI infrastructure through fossil fuel generation risks worsening Britain’s emissions challenges at a time when the country is already confronting the effects of climate change.

"Those promoting the rush for hyperscale AI datacentres seem to be living in a parallel reality where the last 50 years of climate science hasn’t happened, and where we aren’t already experiencing the signs of climate breakdown," said Kat Jones, director of Action to Protect Rural Scotland.

She added, "The conference sessions on AI and hyperscale datacentres seemed to be taking it for granted that onsite gas generation would be needed if these ultra energy intensive developments are to happen, due to the impossibility of connecting them to our congested grid."

Read more: US tech giants lobbied EU to hide datacenter pollution data

  • climate targets
  • data centers
  • Artificial Intelligence
  • UK
  • Natural Gas

Most Read

A document that was included in the U.S. Department of Justice release of the Jeffrey Epstein files, photographed Wednesday, Feb. 4, 2026, shows an April 2012 International Driving Permit for Epstein. (AP)

Epstein was strangled, forensic expert says after file review: BBC

  • Miscellaneous
  • 16 Nov 2026
Larry Johnson, former CIA analyst, on Al Mayadeen's The Grand Standoff on Saturday, November 22, 2026. (Al Mayadeen English)

China warned Trump not to touch Iran’s oil tankers: Johnson | Excl.

  • Politics
  • 22 Nov 2026
IRGC camera footage shows the moment a US F-16 fighter jet was intercepted by Iran's air defenses over the Persian Gulf, released on Saturday, November 21, 2026 (Screengrab)

IRGC intercepts US F-16 fighter jet over Gulf: Footage

  • Politics
  • 21 Nov 2026
Iranian Professor of English Literature and Orientalist Studies at the University of Tehran, Mohammad Marandi (Al Mayadeen)

Iran will not wait for 'bombs to fall' to retaliate | Excl.

  • Politics
  • 19 Nov 2026

Coverage

All
US Midterm Elections 2026

Read Next

All
People walk on the debris of a shoe and textile factory in the al-Nahda neighborhood of al-Thawra district following Saudi airstrikes on Sanaa, Yemen, Tuesday, Nov. 17, 2026. (AP Photo)
Politics

Saudi strikes hit healthcare facilities in Yemen; 81 attacks in 24 hrs

In the photo of a phone screen, a Google map showing Lake Ontario renamed as Lake America is seen Sunday, August 30, 2026, in St. Louis (AP)
Arts and Culture

Indigenous leaders say Trump can't rewrite history with lake rename

A sign stands at the National Security Administration (NSA) campus in Fort Meade, Md., June 6, 2013. (AP)
Miscellaneous

11 NSA personnel committed suicide in 2026, prompting calls for action

French left-wing party La France Insoumise (LFI) candidate Jean-Luc Mélenchon delivers a speech at a campaign rally in Le Bourget, outside Paris, France, Saturday, Nov. 7, 2026. (AP Photo/Teresa Suarez)
Politics

Melenchon demands 'Israel' to release Gaza doctor Abu Safiya

Al Mayadeen English

Al Mayadeen is an Arab Independent Media Satellite Channel.

All Rights Reserved

  • x
  • Privacy Policy
  • About Us
  • Contact Us
  • Authors
Android
iOS