UK Navy shipbuilder faces delays amid cash shortage at Scottish plant
Cash shortages at Liberty Steel’s Dalzell plant threaten Royal Navy shipbuilding, delaying delivery of fleet support ships.
-
The RFA Fort Victoria fleet solid support vessel is seen in this photo (Royal Navy via Wikimedia Commons)
A key steel supplier for the Royal Navy is facing an uncertain wait for the materials needed to construct three new fleet solid support (FSS) ships due to a cash shortage at Liberty Steel’s Dalzell plant in Scotland.
Sources with knowledge of the situation confirmed that the mill has been unable to begin full-scale production because it lacks the cash flow to purchase steel slabs, despite an order to supply 34,000 tonnes of plates for the navy vessels.
The Dalzell plant’s troubles reflect broader financial pressures on companies owned by metals tycoon Sanjeev Gupta. Gupta’s GFG Alliance has lost control of several operations since the 2021 collapse of its key lender, Greensill Capital. In August, he lost control of Speciality Steel UK, which was deemed “hopelessly insolvent”.
Dalzell itself has not filed accounts for five years. Gupta is under investigation for failing to file accounts and is subject to a long-running fraud probe by the UK Serious Fraud Office.
Sir David Murray, a Scottish metals magnate, called on the UK government to intervene, echoing measures previously taken at other steelworks. Murray, a former owner of the Rangers football club, said he is prepared to take over and could restore profitability within two years with a £50 million (around $67 million) investment.
“It’s a terrible error of judgment to remain idle when the British economy should have the capability of rolling wide steel which could be supplied to customers like Harland & Wolff and BAE Systems with new naval contracts 17 miles from the mill,” Murray said.
Impact on Royal Navy shipbuilding
The 216-metre FSS ships, designed to carry munitions, food, and supplies for the Royal Fleet Auxiliary, are being built in Belfast by the Spanish state-owned shipbuilder Navantia. The first ship, RFA Resurgent, is scheduled for delivery in 2031.
The contracts were intended to secure UK employment and maximize the use of domestic suppliers. Navantia took over the Harland & Wolff site in Belfast last year after its British owner collapsed.
Liberty Steel’s cash shortage has prevented it from purchasing slabs from British Steel in Scunthorpe. While workers continue to receive 80% of their salaries, production has been limited to small trial runs, processing roughly 1,000 tonnes, equivalent to three days of normal output. Industry figures remain sceptical about the plant’s ability to resume full production soon.
Murray, who attempted to acquire the plant in 2015 before it was sold to Gupta, urged the government to act. He suggested a “pre-pack administration” sale could secure continuity and protect UK industrial capabilities. A Liberty Steel spokesperson said the plant “is fulfilling” the Navantia order and expects trial production to resume shortly. The company highlighted that UK trade actions and tariffs are expected to help Dalzell ramp up production and support domestic industrial policy.
Read more: 'Official sensitive' inner system of UK submarine found in pub toilet
From naval powerhouse to structural decline
The uncertainty surrounding the fleet solid support programme comes as the UK Royal Navy faces mounting structural and operational challenges that have increasingly constrained its ability to sustain a global presence. The service is operating with historically low numbers of frigates and destroyers, leaving escort forces stretched as older vessels are retired faster than replacements enter service.
Ageing platforms have compounded the problem as key assets, including Type 45 destroyers and parts of the submarine fleet, require extensive and costly maintenance, reducing overall availability and limiting the navy’s ability to sustain prolonged deployments. These constraints have been reflected in difficulties maintaining commitments in theatres such as the Red Sea, while reducing presence in strategically vital regions, including the North Atlantic.
Procurement delays and past underinvestment in warship construction have also begun to take effect. Progress on new builds has been slow, while newer platforms have faced technical setbacks. The Queen Elizabeth-class aircraft carriers, intended to anchor the navy’s power projection, have encountered repeated issues ranging from propulsion failures to leaks, affecting operational readiness and reliability.
Alongside material challenges, the Royal Navy is grappling with significant manpower shortages. Recruitment difficulties and gaps in specialist skills, particularly within the submarine service. Analysts have also pointed to an erosion of long-term strategic planning and analytical capability, limiting the Navy’s ability to adapt coherently to evolving threats.
These pressures are unfolding against a backdrop of sustained budgetary constraints and rising equipment costs. At the same time, heightened global tensions and expanding commitments, particularly linked to Russia and China, are placing additional demands on a force already operating at the limits of its resources.